Project Value
$4.1M
- Site clearing and bulk earthworks
- Construction of a drainage channel
- Construction of 2 separate asphalt carpark areas
- Installation of services including new electrical and lighting
- Installation of hydraulic works including drink fountains and automated irrigation system.
- New amenities with effluent disposal system
- Over 3500m2 of concrete pathways
- Design and construction of asphalt pump track
- Numerous furniture items and picnic shelters
- Construction of a large feature playground area
- Installation of fitness and nature play works through the park
- Construction of 2x Dog off leash areas including agility equipment
- Construction of timber bridges
- New entry features
- Planting and turf areas
- Playground equipment
- Landscape soils and mulches